Skip to content
Early Learning

St Albans Kindergarten

14 Modules 5 month project duration 66-Person Kindergarten 501 SQM
All Projects
Key Challenges
  • Narrow residential streets requiring carefully coordinated transport logistics
  • Overhead power lines impacting delivery and crane operations
  • Designing around an existing sewer easement that could not be relocated
  • Delivering a staged project that included demolition of the existing kindergarten, removal of the community playground and construction of a new council car park

Grove delivered the new 66-place St Albans Kindergarten for the Victorian School Building Authority (VSBA) and Brimbank City Council, providing a modern, purpose-built early learning facility for the local community.

The project utilised 14 modular units, manufactured off site over four weeks before being transported and installed on site. Despite the challenges of narrow residential streets and overhead power lines, the building was successfully installed over three days through careful planning and coordination.

From site possession to handover, the project was completed in just five months.

The scope extended well beyond the kindergarten building itself and included the removal of an existing community playground, demolition of the former kindergarten following handover, and the design and construction of a new 10-space car park within the adjoining council roadway.

To maximise the available site, the building was carefully designed around an existing sewer easement that could not be relocated, while two external staircases provide safe and convenient access from both the main entrance and rear playground.

This project marks the third kindergarten Grove has delivered in partnership with Brimbank City Council, demonstrating our proven capability in delivering high-quality modular early learning facilities that meet the unique requirements of live community environments.

Project Highlights

  • Client: Victorian School Building Authority (VSBA) & Brimbank City Council
  • Facility: 66-place kindergarten
  • Modules: 14
  • Factory build time: 4 weeks
  • Building installation: 3 days
  • Project duration: 5 months from site possession to handover
  • Additional works: Removal of existing community playground, demolition of the former kindergarten, construction of a new 10-space car park, and integration of the building around an existing sewer easement.

Explore more

Early Learning
14 Modules 5 month project duration 66-Person Kindergarten 501 SQM
St Albans Kindergarten
St Albans, Victoria
Early Learning
28 Modules 3,050 SQM 78 working days on site 132-Person
Manor Lakes Kindergarten
Manor Lakes, Victoria
Education
29 Modules 10-module classroom 1-module toilet block Refurbished 4-module
Laa Yulta Primary School
Mambourin, Victoria